HVDC TRANSMISSION LINES

ยฑ660kV HVDC Transmission Line Project

System Studies, Contract Assistance, Design Review, Construction Support, Quality Assurance, Operation & Maintenance, Training & Technology Transfer and Construction Supervision.

 

Total Project Cost โ€“ US$ 1658.34 Million
Barqaab Share โ€“ 70% (Local Component)
Date of Commencement โ€“ March 2018
Date of Completion โ€“ February 2021

 

SCOPE OF THE PROJECT

HVDC 660 kV Bipole Transmission Line approximately 870km from Matiari to Lahore
HVDC Converter Station, Lahore
HVDC Converter Station, Matiari
Three Repeater Stations
Grounding electrodes and Electrodes Lines at Matiari and Lahore.